GuidelinesBy procedure2026.11.14
Veterinary Medical Device Import Cost and Timeline — A Table Separating Government Fees and Processing Periods from Preparation Costs and Periods
Seeing that the product approval fee is KRW 10,000, it is easy to assume the whole cost of import preparation is small too. The fee paid to the government and the cost of bringing the product to a state ready for application must be written on different lines. Based on the fees per application in Annex 4, the Government24 processing periods by review type with the exclusion of Saturdays and public holidays, and the 60-day supplementation provision, this guide sets out a cost table, a schedule before and after filing, and two fictional examples. Agency fees are quoted separately.
Key takeaway — Cost has three lines: government fees (Annex 4), preparation costs (testing, certificate issuance, translation, document preparation) and agency fees. Time has three segments: the preparation period before filing, the processing period given by Government24, and the supplementation period. No line or segment substitutes for another. Subtracting only the processing period from the delivery date misses the margin needed for obtaining documents and for supplementation.
This article is based on the Rules on the Handling of Veterinary Pharmaceuticals, etc. (MAFRA Ordinance No. 741, in force 31 October 2025) with Annex 4, three Government24 civil-service guidance pages, and the APQA notices Regulation on the Review of Technical Documents, etc. for Veterinary Medical Devices (No. 2020-18) and Regulation on the Scope and Classification of Veterinary Medical Devices (No. 2021-36), as checked on 6 October 2026. Route, documents, test data, certificates and quality requirements were each covered in the preceding articles; this article brings those results together as cost and schedule.
Government fees and processing periods: look at them per application
| Application | Fee (Handling Rules Annex 4) | Processing period (Government24 guidance) |
|---|---|---|
| Veterinary medical device and veterinary IVD import business license | KRW 30,000 (point 11) | 10 days in total |
| Veterinary medical device manufacturing (import) notification | KRW 10,000 per item (point 3) | 10 days in total |
| Veterinary medical device manufacturing (import) product approval | KRW 10,000 per item (point 3) | Items not requiring review of technical documents, etc.: 10 days in total · technical document review, Class 1 and 2: 40 days in total · Class 3 and 4: 60 days in total · safety and effectiveness review: 80 days in total |
| Change approval or notification for a manufactured or imported item | KRW 5,000 per item (point 4) | |
| Sales or rental business notification (change notification) | KRW 10,000 (point 7) | |
| English certification of approved particulars | KRW 5,000 (point 13) |
Government24 states that processing periods of 6 days or more are calculated excluding Saturdays and public holidays. An applicability review request under Article 3 of the Scope Notice is notified within 7 days, and a reclassification application under Annex 8, point 4 is reviewed and decided within 60 days. These periods, too, are clocks that run after filing.
Before simply multiplying the number of products by the fee, check the unit of application. Article 3(1) of the Approval Notice provides that products in the same product group may be applied for under one product approval or notification, so the number of applications depends on the model configuration.
Cost table: record preparation work as separate rows
| Item | Needed? | Basis for the estimate | Owner | Expected completion |
|---|---|---|---|---|
| Government fees | Fixed per application | Annex 4 | RA | Filing date |
| Testing and assessment (items that existing data cannot cover) | Under review | After checking the issuing body, identity and three-year requirements of the data held | Manufacturing source, test laboratory | After the quotation reply |
| Issuance of certificates of manufacture and sale | Common to approval and notification | Issuing country's body and format | Export sales, manufacturing source | Per the issuing body's guidance |
| Translation and document preparation | After the documents are fixed | Volume, language | RA | |
| Technical document drafting and comparison | Approval route | Number of application items | RA | |
| Application agency | Optional | Scope of work | Agency | Quoted separately |
Leave unconfirmed items as ‘under review’ rather than filling them in as zero. Whether testing is needed can only be decided after checking the issuing body, model name and raw material identity, and three-year requirements of the reports held, so obtaining retesting quotations before reviewing the reports may waste data that could have been used. Overseas issuance costs vary by country and document format.
Schedule: connect before and after filing
| Step | Content | Owner | Completion condition | Reply that blocks the next step |
|---|---|---|---|---|
| 1 Classification and route | Confirm notice-designated item, class and Class 1 equivalence | RA | Approval or notification route fixed | Review result under Article 3 of the Scope Notice |
| 2 Company preparation | Import business license documents, import establishment facilities | Management support, operations | Statement of facilities and equipment completed | Warehouse and test outsourcing fixed |
| 3 Manufacturer document collection | Product information, technical documents, test data, certificates | RA, export sales | Status complete for every item | Manufacturer reply |
| 4 Filling the gaps | Additional testing, certificate issuance, translation | Test laboratory, manufacturing source | Data requirements met | Testing and issuance schedule |
| 5 Application comparison | Confirm model name, raw materials, specifications and manufacturing source match | RA | Zero discrepancies | |
| 6 Filing and review | File the import business license and product applications | RA | Processing period elapsed | Request for supplementation (once, up to 60 days) |
| 7 Sales preparation | Product-specific requirements such as labeling and customs clearance | Operations | Ready for release |
Distinguishing tasks that run in sequence from those that can run in parallel shows which reply is holding up the next piece of work. Steps 2 and 3 can run in parallel, and the scope of step 4 depends on the results of step 3. The processing period and supplementation period after filing apply only to step 6.
Fictional example: same class, different state of preparation
This is a fictional example for illustration. Suppose fictional products J and K are preparing for approval in the same class. J holds test data matching the application model and current certificates; K has not confirmed the tested model or the list of raw materials. The same government fee does not mean the same preparation cost and time for the two products.
- J must still review the issuing body, identity and three-year requirements of the data and the submission format. Once that review is done, step 4 is short.
- K first checks whether the gap can be resolved with additional manufacturer documents and, if testing remains, obtains cost and time quotations. Step 4 becomes the bottleneck in the schedule.
This example does not present a specific amount or approval deadline; it compares the starting points for budget and schedule.
Common misunderstandings
| Common explanation | What the provisions and guidance provide | What to check |
|---|---|---|
| The KRW 10,000 fee is the total cost | Annex 4 is the amount paid to the government. | Preparation cost rows |
| It is done in 40 days | That is the processing period after filing, excluding Saturdays and public holidays. | Preparation and supplementation periods |
| Supplementation can be requested several times | Once, up to 60 days, with a 10-day reminder if not submitted. | Data requirements before filing |
| One application per product | Products in the same product group can be applied for under one application. | Model configuration |
| Subtract only the processing period from the delivery date | Obtaining documents, testing and issuance come first. | Schedule steps 1 to 5 |
| Agency fees include the government fees | Fees and agency fees are shown separately. | Quotation items |
The fees and statutory periods for human-use medical devices are in the one-page table of medical device fees and statutory periods. Veterinary devices have different bases and amounts, so that table is not used as it is. The details of each step are in the earlier articles classification and application route, import business license and product import approval or notification, test report requirements, certificates of manufacture and sale and quality management distinction.
Documents that speed up the review if prepared before inquiring
- Product list and the desired introduction date
- Status of test data and certificates of manufacture and sale held (issuing body, date of issue, model covered)
- State of preparation on the company line (facilities, test outsourcing plan)
Please mention veterinary medical devices in your message when you use the veterinary import schedule review inquiry. We will review the application route and document gaps and advise on the scope of work and schedule, separating government fees, preparation costs and agency fees. Agency fees are quoted separately according to the scope of review and application. The scope of services is on the veterinary medical device services page.
Prepared and sources checked: 2026-10-06. Sources: Rules on the Handling of Veterinary Pharmaceuticals, etc. Article 56, Annex 4, Annex 8 point 4 · Government24 import business license · manufacturing (import) notification · manufacturing (import) product approval · Regulation on the Review of Technical Documents, etc. for Veterinary Medical Devices Article 7 · Regulation on the Approval, etc. of Veterinary Medical Devices Article 3(1) · Regulation on the Scope and Classification of Veterinary Medical Devices Article 3. The cost table, schedule and fictional example are our own practical tools and do not present an actual quotation or approval outcome.
Frequently asked questions
- Q. What is the product approval fee for a veterinary medical device?
- Article 56 and Annex 4 of the Handling Rules set the approval of a manufactured or imported item at KRW 10,000 per item, its change approval or notification at KRW 5,000 per item, the veterinary medical device import business license at KRW 30,000, a sales or rental business notification at KRW 10,000, and the English certification of approved particulars at KRW 5,000. These amounts are the fees paid to the government and do not include testing, issuance, translation or agency costs.
- Q. If it is Class 2, will approval be issued within 40 days?
- Government24 gives the product approval processing period as 10 days in total for items not requiring review of technical documents, etc., 40 days in total for Class 1 and 2 requiring technical document review, 60 days in total for Class 3 and 4, and 80 days in total for items requiring a safety and effectiveness review, and states that processing periods of 6 days or more are calculated excluding Saturdays and public holidays. This is the processing period after filing; the preparation period before filing and any supplementation period are not included.
- Q. How much longer does a request for supplementation add?
- Article 7(2) of the Review Notice provides that supplementation of data may be requested only once, with a period of up to 60 days, and that if it is not submitted within that period a reminder may be issued to supplement within 10 days. The time spent on supplementation is added on top of the processing period, so screening the data against the requirements before filing is the key to the schedule.
- Q. How much are the agency fees?
- Agency fees for veterinary medical devices are quoted separately for every item, because the workload varies with the item, class and state of the documents held. The quotation separates the government fees, external costs such as testing, issuance and translation, and the agency fees.